School News
Welcome to the Benson Public Schools Blog!
To view a complete post and any attached pictures or documents, please click on the blog title.



Recent Posts
1  2  3  4  5  6  7 

Starting Wednesday, June 19th, the circle drive at Benson High School will no longer be available. Security fencing will be installed. Access will be from the high school parking lot entrances. The main doors will be open to enter the high school.

Please use care when entering and exiting near construction sites.  Construction will take place in various phases and areas at the high school and Northside Elementary until completion, expected in 2021.

Please share this information with students, family, friends and community members and remember to use extreme caution by keeping a safe distance from construction sites.

We appreciate your cooperation and respect for the safety of everyone involved in this exciting project for our school and community!

Sincerely,
Dennis Laumeyer
Benson Public Schools Superintendent

Safety Map 2019

Posted by lori.eix  On Jun 26, 2019 at 6:50 AM
  

East Gym construction continues to progress.  Attached is a photo with the wood floor installed.  The next steps are to stain part of the floor and paint lines.  Bleachers will be set on May 28th.  The East gym is scheduled to be ready for use on June 1st

  • Bid Package #1 was opened on May 16th.  This bid package includes site preparation, excavation, and demolition at BHS.  Bids came in under budget so if there are no major surprises, we should stay on budget.  The plan is for the auditorium to be demolished this summer before school starts.
  • The architects and engineers are working hard to finish drawings and specs for NS work.  The NS bid package is expected to be released in early June and bid opening mid-June.  We hope bids come in favorable.  Work is expected to start in July.  There will be some inconveniences at NS during construction.  The main front doors will not be usable due to construction and parking on the East side of NS will be used for construction equipment and materials.  Attached is a NS rendering.
  • BHS bid package is expected to be released in August with work to begin in September.
  • The 10,000 gallon fuel oil tank outside the BHS cafeteria was removed to be ready for site preparation and excavation for the auditorium. 

It is exciting to see all of the planning coming together and people getting to see exterior construction starting!  Thank you in advance for your patience during the construction process. Benson is going to have amazing spaces that everyone will be proud of. Thank you for all of the staff input on this process.

East Gym Floor

Northside Sketchup

Fuel oil 10,000 gallon tank

Posted by lori.eix  On May 16, 2019 at 9:29 AM
  

East Gym: Progress is being made on the East Gym remodel. As shown in the attached photo, the ceiling has been painted and baskets are being mounted. They are also painting the walls. Electrical has been roughed in. Lights are scheduled to be installed the week of March 25th. In addition, the second attachment shows workers replacing the roof. Fortunately bids came in lower than expected and the roofing project was able to be included in the overall gym remodel. The roof was in need of replacement.

East Gym 


East Gym Roof


East Gym
: For many years there has been a water leak into the East Gym space. To prevent any damage to the new wood floor, the architect and engineer are finalizing plans to mitigate the water issue. Most likely it will involve digging a trench at the south and east walls, adding water barrier, adding drain tile, and filling back in. The plan is to have the exterior water mitigation work completed in the next 2-3 weeks and have the floor installed in early May. The bleachers are scheduled to be installed mid-May.

Main Construction Project: After many meetings September 2018-March, 2019 the architects and engineers are working hard completing drawings and writing specs, though there are still details and meetings to be held. Bid Package #1 – BHS site work is schedule to go out in April with a May bid opening. This bid package will involve demolition of the auditorium and related site preparation work. NS bid package is scheduled for June release and the BHS bid package is scheduled for July release.

Posted by lori.eix  On Mar 28, 2019 at 1:48 PM
  

East Gym: Construction is underway on the new “East” Gym. Part of the construction project will include repaving, and most likely redesign of the BHS parking lot. For more safety and efficiency we are looking at having busses pick up and drop off on the north side of BHS and parent pick up on the south side of the school. There will be work required to make bus drop off and pick up on the north side, perhaps making that street a one-way. Preliminary discussion has been held with Chief Hodge and SRO Paula Wilson. More information will be coming as this phase progresses.

 

Northside Addition: The Benson City Council approved a conditional use permit at Northside for the cafeteria addition and the preschool addition to be within the set-back limits. This is a big step forward. We thank the city council and Mayor for their support.

 

Design and layout meetings continue:  Preschool staff met with the architect to continue design work. Two teachers are going to the new elementary school (Lakeland) in Willmar to get design ideas for classrooms. Preschool staff visited another site to get ideas. There was a meeting on the auditorium as well with the architect and engineer. Much time was put into the auditorium sound and light needs. There is a tremendous amount of detail in an auditorium. Thank you to Brock and the auditorium committee for visiting other auditoriums to get ideas and be prepared.

 

The school board worked with the architect and engineer to decide on mechanical systems at the NS additions and at BHS.

 

The school board will be holding a work session. One of the agenda items will be to get an update on the auditorium from the architect, engineer, and Brock.

 

The Construction Manager (CM) is analyzing the drawings to this point. He will be contacting area contractors to get real time costs on different parts of construction. The CM will be giving a budget report and timeline to the school board at the February meeting. This is the job of the CM, to make sure the project is on budget and completed on time. This will be their first report, with more to follow as we work through construction.

 

The plan right now is to demolish the auditorium before school begins for the 19-20 school year. If this happens, the main BHS entrance may not be available for the school year. This is not definite, however it may be a possibility.

 

The NS main entrance may also be disrupted as construction happens on the cafeteria. Still working on options at NS.

 

Please know that parking will be limited around BHS and NS during periods of construction and we may have longer walks to get to the buildings.

 

While nothing is visual at this point, much progress is being made and many exciting things happening. Thank you to the staff for how prepared you have been for design and layout meetings and for having open minds to new ideas. This is fun and exciting stuff happening in our schools!

 

While the footprints (layouts) of the main construction areas are pretty well finalized, some of the interior work is yet in design phase.

 

Posted by lori.eix  On Mar 28, 2019 at 1:43 PM
  

‚ÄčEast Gym‚Äč: Breitbach Construction gave an update on the East gym project. Initial wiring is completed and fire suppression is completed. Painters are now painting the ceiling. Basketball hoops are scheduled to be mounted next week and electricians will begin to hang lights. Water has come through the block onto the floor. This has been an ongoing problem. Breitbach is putting together a plan to mitigate the water infiltration so not to damage the wood floor. Likely, this will mean digging around the foundation, applying a water proof sealant to the exterior, putting in drain tile, and then filling with rock to drain. Grade for the original building was to be 2’. When the choir room was added, the grade went to 5’ so it is suspected that water proofing went up 2’, but not 5’. Plans for the main projects continue to move forward. Drawing and specs are being worked on. Bid package #1 – BHS site prep work is scheduled to be released in April, with bid opening in May. This includes demolishing the auditorium.

CM Agreement: The board approved the Construction Management Agreement.

ARY Agreement: The board approved the agreement with ARY (architects).

Posted by lori.eix  On Mar 28, 2019 at 1:39 PM
  
1  2  3  4  5  6  7 
 
Website by SchoolMessenger Presence. © 2020 Intrado Corporation. All rights reserved.